  Sectors> IRD>Progress  
Schemes Constructed by IRD (Sharaid Foot Suspension Bridge)
Suspension Bridge
The main problem was the communication between Sharaid and surrounding villages on the other side of the river. There used ti be a traditional wooden cantilever bridge, which link Shariad with other villages, but during the devastating 1992 flood, this bridge swept away .The community used to construct the temporary wooden bridge each year and the community feel a dire need to construct permanent bridge.
The bridge constructed by PCDP links Sharaid , Kuz Seer ,Bar Seer and the other surrounding villages .The total direct beneficiaries are 963 and there will be indirect beneficiaries will use occasionally use the bridge. The villagers have about 1099 Livestock and they are using the bridge for crossing the river.
Kuz Paro Water Mill/River Protection Spur

Kuz Paro is first village along the main Bar Palas foot track .It is accessed by Pattan to Ziarat road about 26 Km (Up to Sharial Nallah) and beyond it three km on foot track .There were 8 water mills before the 1992 flood ,facilitating the maize grain grinding for the surrounding villages that includes Kuzparo,Barparo,Mughal Abad and Kalyar.
The Community based Organization formed with the aim of Biodiversity Conservation in Feb, 2002, with the Motivation of PCDP staff. As the CBO formed, they repeatedly requested for construction of Water mills and river protection spur. Site is located near to the high flood level but there was no other communal land .Keeping in mind the risk involved and repeated request of Kuz and Bar Paro CBOs , 400 feet long channel and a protection spur [Gabion Materials] (2700 cft) was constructed at the site.
The Contribution for the mill from all the surrounding villages is the indicator of common interest. PCDP constructed River Protection Spur and water channel but the water mill is still under constructionBack to Top

Kundal Irrigation Channel
Kundal is one of the remotest hamlet of Bar Palas and Situated about 46 Km from Pattan (According to the statement of Local People). The Kundal is accessed by road up to Sharial nallah, which is 26 Km from Pattan and beyond it, is accessed by feet.
There are 873 persons living in 113 Households. The People have dependency on Agriculture, Live Stock and the other natural Resources. The People are poor and mostly work as an unskilled Laborer in other Parts of the Country.
The Community of Kundal, organized in a CBO by the Motivation of PCDP in Nov.2001.
The CBO requested the Project through a resolution to help them in the development of irrigation Channel. The Channel was closed somewhere 50 years back. Some of the village Influential develops another channel but they were not allowing the other people to irrigate their lands. The Construction of the Channel will facilitate the work of all the People. The total length of channel is 5238 feet (1.6 Km). The nature of Channel is unlined but includes aqueduct, dry stone rubble masonry, as well as blasting of rock at the required points. The channel is benefiting 50% population of Kundal village.Back to Top
Gulbagh Irrigation Channel
The channel was previously constructed by the community but the flood has washed away the channel as well as the channel is passing through sliding area. The CBO Requested to help them and providing pipeline for the specific sliding area. THE PCDP provided 560 feet long pipe and constructed intake as well as retaining wall. Back to Top
Harran Irrigation Channel
Haran, the 3rd village after Seer Ghazi abad on the Pattan –Sharakot Road in Kuz Palas Valley. Total inhabitants in the village are 3025 living in 275 households [According to the COP office file Record].
The villager organized in the shape of the Community based Organization (CBO) with the aim to conserve the natural resources and Biodiversity Conservation of Palas valley in May 2001. The CBO through a resolution, asked for improvement of the irrigation channel.
The Haran has cultivatable land of 100 Jribs irrigated by two channels. The Channel damaged in the flood and rehabilitated in Khushal Pakistan Program but it again damaged. The CBO through a resolution, asked for improvement of the irrigation channel. The works PCDP did include 600 cft Structure Excavation in Hard Rock Materials, Intake structure and 500 feet Pipe Channel.
Back to Top
River Protection Spur Gaddar
On main track in bar Palas near Gaddar, the River Mushagah directly hit the track and the people in summer, when the water level in the river was high enough could not use the path and was dangerous if used. The PCDP Constructed the Protection Spur to make the track comfortable and useable through out the year. It is facilitating the entire population of Bar Palas.Back to Top
Rest Huts
Two Rest hut Huts constructed in Dassu and Pattan.
Up gradation of foot track
10 km from Paro to Sharaid {5km point blasting and 5km and 5km point blasting)
10 km Shraid to kundal upgraded
1km from Maidan to sharial upgraded
The track main achievement is the shifting of load form the heads and shoulders of men and women of bar palas to the donkeys.Back to Top
Material Store at Pattan
A store for stacking of materials constructed at pattan
Schemes Under Construction
1. Suspension Foot Bridge Bngaha Bar Palas
This is located on main track and will facilitated the entire community of bar Palas
2. Suspension Foot Bridge pherorgah Bar Palas
This is located on main track and will facilitated the entire community of bar Palas
3. Irrigation Water Channel Scheme Shalkan Abad Kuz Palas Conservation and Development Project
The earthen channel requested to upgrade through lining but it is taking too much time although the length of channel is 1500 feet.
4. Irrigation Water Channel Scheme Bar Gabeer Kuz Palas
It is linking one channel with other to increase the discharge of the existing channel and will irrigate more land.
5. Water Supply Scheme Tawheed Abad Kuz Palas
6. Water Supply Scheme Karo Seer Bar Palas
7. Field Rest hut Hut at Dado Banda Gaddar Bar PalasBack to Top
Schemes Planned

1. Suspension Foot Bridge Gaddar Bar Palas
2. Suspension Foot Bridge Nou Bar Palas
3. Suspension Foot Bridge Shambaila Bar Palas
4. Suspension Foot Bridge Maidan Bar Sharial Kuz Palas
5. Irrigation Water Channel Scheme Kuz Seer
6. River Protection Spur Peach Bella Bar Palas
7. River Protection Spur Hisar Bar Palas
8. River Protection Spur Dum Bella Bar Palas
9. River Protection Spur Wool Bella Bar Palas
10. Field Rest hut Kundal Bar Palas
11. PCDP HQ at Seer Ghazi Abad PalasBack to Top