Field Stories

palas homebirdlife website
EU website
NWFP website
 
 
  Field Stories  
Haran Irrigation Channel in Kuz Palas
Background:

Haran village CBO was formed in October 2001 with 25 members, the majority of whom are either farmers or herdsman. The agricultural land is about 100 “Jareebs” which is irrigated by two channels originating from perennial “nalahs”. The channel irrigating the major chunk of farmland (75 Jareeb) was not operating as a section of it was swept away by a landslide in 2001. This section was constructed under the “Khushal Pakistan Program” but in the very first year of its operation the channel was eroded, reason being poor selection of site.

Dialogue:

Son after its formation, the CBO requested for PCDP support in repairing the disrupted channel. The resolution was backed by majority decision in review of the need for water for their next maize crop.

In light of the prioritized need a survey of the identified irrigation scheme was carried out. The outcome of this survey was that a safer terrain had to be chosen for the channel off-take since the site was vulnerable to land sliding; secondly a pipeline would be laid in the steep ridge as seepage from an open channel would be liable to erosion again. The CBO representatives agreed to the method of addressing the need.

Terms of Partnership:
In the partnership arrangement it was agreed that the CBO would nominate a sub group called Work Committee (WC). On behalf of the beneficiaries, the WC would liaise with the project, arrange community contributions of free, unskilled labor during earthwork/ carriage of pipes/ collection of sand and gravel etc, provide storage space for expensive construction materials, boarding place for workers from outside and nominate trainees for skills enhancement in blasting, masonry etc.

From the project side it was agreed that all purchasable items from the market would be arranged such as tools and implements, blasting, pipes, cement, transportation costs from market to village and skilled labor for masonry and pipe fitting. The agreement was concluded on a snowing afternoon of January in the assembly of nearly 40 people.

Construction:
It seemed that community members considered the whole process ‘a mere formality’ as never before an example is remembered whereby an outside development agency has had such a close collaboration with a beneficiary group in Palas. As the project supplied the tools and implements to the WC it turned to be an eye opener. The WC called an assembly of beneficiaries and formed the work force of unskilled workers from the eight divisions of water in the channel. The WC decided that any member who absented from the communal labor would have to pay a fine (“Nagha”) therefore during the next three months community labor share was never a problem; additionally, Rs 950/- were also collected as Nagha.

Haran Irrigation Channel

A healthy sign of community acceptance and extended cooperation had been that certain improvements in the proposed work, such as concrete lining in channel reaches susceptible to seepage, clearing of debris which had fallen in a channel flowing in a lower contour, were brought forward by the beneficiaries

During the blasting and earthwork, which continued for almost two months on a difficult and steep terrain, the community came all out to support the earthwork alongside the blasting and drilling operator. A community nominee worked alongside as helper to the drill machine operator who was paid Rs 80/day by the project (CBO committed Rs 20/day). Furthermore, the daily record of blasting work was maintained by the Secretary of the CBO.

During the third month of construction, involving masonry and pipeline fitting, the community members collected sand and gravel for masonry work, which was carried out by the mason from the village. For the purchase of 4” diameter pipeline the President of the CBO accompanied the PO to Besham and the pipes were transported from the village to the site by the villagers. These 520ft long pipes were fitted by the pipe fitter engaged by PCDP. The total cost incurred on the scheme is Rs 1,85,000 of which Rs 25,000 of free labor has been contributed by the community.

Trial Testing:
Water was led into the channel on June 12, 2002 by tapping all the available discharge in the nalah. The discharge in channel was measured through float method to be 1.08 cfs. This can sufficiently irrigate 185 Jareeb of agricultural land. The earthen channel down stream is flowing to its brim full capacity. Some overflow is also seen at the intake chamber, which the community is very keen to avoid.

Utilizing the maximum resource. It was decided to raise the intake chamber height by 2 ft and add a larger diameter pipe (length 40ft) in the initial stretch of the pipeline, in order to curtail the 10 % spill over.

Lessons Learnt:

1. Community response to collective labor is rapid and consistent if the scheme is a dire necessity and confidence of the community is attained through the acceptable village leadership.
2. Community is at large in a habit of asking more as to what has been agreed therefore a balance has to be struck between what is reasonable and what is beyond reasonable limits.

Hussain Mustafa, Programme Officer IRDBack to Top